The french doors between Nate and Ben's bedrooms have been removed and we have used this existing doorframe to incorporate closets into both bedrooms, a double width closet in Nate's room and two single closets in Ben's room. Neither room had a closet before.
Check in this weekend again for more updated photos. Next up on our agenda:
- Rest of wallpaper to be removed this weekend by yours truly.
-Electrical to be completed this weekend.
-Framing of hall bathroom and attic adjustments to be completed this week.
-Drywalling to start next week.
-Painting to start on 10/23.
-Floors to be refinished starting 10/27.
-Tile work in kitchen, sunroom, and laundry to be started soon.
-Appliances arrive end of the month.
Phew, that's a lot of work! We're so proud of Andrew's work so far and cannot wait see the progress over these next few weeks. Very exciting!
2 comments:
Oh Liz! The house is looking so great!!! I can't wait to come and visit and see it all. I wish we were able to come and help with all the work being done! Andrew is so great at all of that stuff...miss you guys!
Oh Liz! The house is looking so great!!! I can't wait to come and visit and see it all. I wish we were able to come and help with all the work being done! Andrew is so great at all of that stuff...miss you guys!
Post a Comment